Milestone |
Dates
|
|
FORMATION OF MANGALORE HARBOUR PROJECT |
21st Apr. 1962
|
|
DECLARATION OF NEW MANGALORE PORT AS MAJOR PORT |
4th May 1974
|
|
FIRST SHIP, M.V.SATSUMARU BERTHED |
10th Jun. 1974
|
|
FORMAL INAUGURATION OF THE PORT WITH 3 GENERAL CRGO BERTHS |
11th Jan. 1975
|
|
OIL JETTY(NO.9) COMMISSIONED |
12th May 1975
|
|
FORMATION OF PORT TRUST BOARD |
1st Apr. 1980
|
|
COMMISSIONING OF IRON ORE BERTH(KIOCL JETTY) |
15th Aug. 1980
|
|
COMMISSIONING OF ADDL.GEN.CARGO BERTH(NO.5) |
1st Feb. 1984
|
|
COMMISSIONING OF 2ND ADDL. BERTHS(6&7) |
7th Nov. 1989
|
|
NMPT BECAME AN ISO 9001:2008 PORT |
27th Oct. 2003
|
|
NMPT BECAME THE FIRST MAJOR PORT IN INDIA ACCREDITED WITH ISPS |
29th Nov. 2004
|
|
DEEP DRAFT MULTI PURPOSE GENERAL CARGO BERTH COMMISSIONED |
14th Feb. 2006
|
|
BIO-METRIC ATTENDANCE SYSTEM FOR CARGO HANDLING WORKERS IMPLEMENTED |
1st Dec. 2006
|
|
CRUISE LOUNGE COMMISSIONED |
11th April 2008
|
|
NMPT GOT ISO 14001:2004 CERTIFICATION FROM IRQS |
22nd Feb. 2011
|
|
BERTH No. 15 became operational |
Dec. 2011
|